Costs
==Costs==
* Where stones are in short supply, there are increased costs associated with their acquisition and transport. * Labour for construction: 6-16 days per hectare. Annual maintenance: 3-18 days per hectare.* If bunds are formed in a terrace-like design, the labour required for construction is estimated at 150 to 350 person days/ha for terraces and cut off drains. The cost of these structures is approximately $60-460/ha.
Akvopedia-spade, akvouser, bureaucrat, emailconfirmed, staff, susana-working-group-1, susana-working-group-10, susana-working-group-11, susana-working-group-12, susana-working-group-2, susana-working-group-3, susana-working-group-4, susana-working-group-5, susana-working-group-6, susana-working-group-7, susana-working-group-8, susana-working-group-9, susana-working-group-susana-member, administrator, widget editor