Changes

Jump to: navigation, search

Talibon Slaughterhouse Wastewater Retrofit

No change in size, 23:29, 2 September 2016
The Existing Wastewater System
The facility layout is represented in the diagram.  The left-most box represents the digestive tank, the middle box represents the first open pit, and the right-most box represents the second open pit. The main concern with the existing layout is that it appears to be too small to accommodate all of the flow and provide the required treatment. Biodigesters that are designed to accomplish anaerobic digestion of slaughterhouse wastewater are generally designed for detention times of between 7 and14 days. Therefore, it appears that the digestive tank is significantly undersized to accomplish complete anaerobic digestion at the design flow. The pits are also on the small size given the projected wastewater flows. They will operate as anaerobic pits, which also require a sufficient detention time to accomplish proper treatment.
| style="width: 216px" | [[File:Talibon.gif|right|180px200px]]
|}
Akvopedia-spade, akvouser, bureaucrat, emailconfirmed, staff, susana-working-group-1, susana-working-group-10, susana-working-group-11, susana-working-group-12, susana-working-group-2, susana-working-group-3, susana-working-group-4, susana-working-group-5, susana-working-group-6, susana-working-group-7, susana-working-group-8, susana-working-group-9, susana-working-group-susana-member, administrator, widget editor
30,949
edits

Navigation menu